Data center 1 and 4 scheduled maintenance

Monday, 25th July, 2011 08:29 UTC

Update (11:38 UTC) – Data center 4 migration completed. Monitored downtime for the service was 5 minutes.

Update (11:32 UTC) – Data center 1 migration completed. Monitored downtime for the service was 15 minutes.

On Saturday 30th July 2011, at 11am UTC we will be performing maintenance work on data centers 1 and 4. The service might be unavailable for up to 1 hour. However, we are expecting downtime to be substantially less. Customers on other data centers will not be affected.

Data center 3 and 5 scheduled maintenance

Sunday, 17th July, 2011 11:33 UTC

Update (11:30 UTC) – Data center 3 migration completed. Monitored downtime for the service was less than 3 minutes.

Update (11:20 UTC) – Data center 5 migration completed. Monitored downtime for the service was 6 minutes.

On Saturday 23rd July 2011, at 11am UTC we will be performing maintenance work on data centers 3 and 5. The service might be unavailable for up to 1 hour. However, we are expecting downtime to be substantially less. Customers on other data centers will not be affected.

Trial users data center move

Wednesday, 6th July, 2011 08:28 UTC

UPDATE: the migration has completed successfully. The measured downtime for our trial users was 3 minutes.

On Saturday 9th July 2011, at 11am UTC we will be migrating our trial users to a new data center. The trial service might be unavailable for up to 1 hour. However, we are expecting downtime to be substantially less. Paid customers will not be affected by this change.